Bronx FISP Facade Inspections: An Owner's Guide to Local Law 11
Along the Grand Concourse, in Riverdale, and across the South Bronx, many apartment buildings are tall enough to fall under the Facade Inspection & Safety Program, known as FISP and still widely called Local Law 11. The program exists because loose brick, cracked terra cotta and failing parapets can fall onto the sidewalk. For owners, FISP is a recurring legal obligation with real consequences when it is missed or when an Unsafe condition is left unrepaired. This guide covers how the program works in practice.
Which Bronx Buildings Are Covered
According to the Department of Buildings, buildings taller than six stories must have their exterior walls inspected every five years and a technical facade report filed with DOB. The requirement comes from the NYC Construction Codes and the Department's facade rule. The inspection is called a critical examination and covers the exterior walls and appurtenances such as balconies, fire escapes and railings.
How stories are counted can be less obvious than it looks, especially for Bronx buildings on sloping lots. DOB publishes a FISP universe map. If you are unsure whether your building is included, confirm it there rather than guessing.
Cycle 10 and How Sub-Cycles Work
FISP runs in five-year cycles. The current cycle is Cycle 10, which DOB's sub-cycle diagram shows running from February 21, 2025 to February 20, 2030. Within each cycle, buildings are assigned to sub-cycle A, B or C based on the last digit of the tax block number:
- Sub-cycle 10A: blocks ending in 4, 5, 6 or 9
- Sub-cycle 10B: blocks ending in 0, 7 or 8
- Sub-cycle 10C: blocks ending in 1, 2 or 3
Each sub-cycle has its own filing window. The 10A window opened on February 21, 2025. For your exact window, check the DOB Facade Compliance page and its Cycle 10 diagram. DOB has also allowed early filing for sub-cycles 10B and 10C, including for owners who missed Cycle 9 and have paid the applicable civil penalties. DOB's filing instructions state that a report is to be filed within 60 days after the inspection is completed, so plan the inspection with the filing window in mind.
The QEWI and the Report
The inspection must be performed by a Qualified Exterior Wall Inspector (QEWI), a registered architect or engineer who meets DOB's experience requirements for facades over six stories. The QEWI or their team examines the walls, including hands-on inspection from a scaffold or rope access where the rules require it, then files the technical report through DOB NOW: Safety. The report describes the building, its wall materials, the conditions found, photographs, and the QEWI's classification of the facade.
Safe, SWARMP and Unsafe: What Each Rating Means for You
Safe
No unsafe conditions and nothing that needs repair within the cycle. You keep up routine maintenance and prepare for the next cycle.
SWARMP
Safe With a Repair and Maintenance Program means conditions are not yet hazardous but need attention. The QEWI assigns an expected date by which each condition would become unsafe, somewhere between one and five years out, and the owner must complete repairs before that date. DOB states that the same conditions cannot stay SWARMP in consecutive cycles. Items left unrepaired become Unsafe.
Unsafe
An Unsafe condition is a hazard to the public. DOB's process is strict:
- The QEWI notifies the owner, who must immediately install public protection such as a sidewalk shed, fencing or netting
- The condition is reported to 311, and the QEWI files a notification in DOB NOW
- The full Unsafe report is filed
- Repairs are required within 90 days, and if they cannot be finished, the QEWI files an extension request
- After the repairs, an amended report shows the facade is Safe or SWARMP, and the protection can come down
DOB states that owners are liable for civil penalties starting 90 days from the date the initial Unsafe report is filed unless that period is covered by acceptable extension requests.
Sidewalk Sheds and Repair Permits
Many long-standing sidewalk sheds in the Bronx are there because Unsafe conditions were never fully repaired. A shed needs its own permit, and the facade repairs themselves, such as masonry rebuilding, parapet work or lintel replacement, usually require DOB work permits filed by a registered design professional, plus a site safety plan where applicable. Getting the repair filings approved quickly is often the biggest factor in how long a shed stays up. The sooner the repair drawings and permits move, the sooner the amended report can be filed and the shed removed.
A Practical Timeline for Owners
Start early in your sub-cycle. Hire the QEWI, budget for access equipment, and assume the inspection may uncover repairs that need design and permits. If your last report was SWARMP, check those items first, because they will not carry over as SWARMP again. Keep the records from prior cycles, since the QEWI will compare conditions over time.
AM Expediting Drafting & Design Works LLC helps Bronx building owners with the permitting side of facade compliance, including sidewalk shed and repair filings, drawings, and coordination with your QEWI so that permit delays do not hold up an amended report. If your Bronx building is in Cycle 10, call (718) 971-0617 to review your sub-cycle and next steps.
Stay on Track With FISP
We handle permits for facade repairs and sidewalk sheds and coordinate with your QEWI. Call (718) 971-0617 to discuss your Bronx building.
(718) 971-0617 — Call NowAM Expediting Drafting & Design Works LLC · 76-18 Rockaway Blvd, Woodhaven, NY 11421 · (718) 971-0617 · Serving Queens, Brooklyn, Manhattan, the Bronx and Staten Island.